At the beginning of the year, a company estimated a predetermined plantwide overhead rate of $8.50 per machinehour. Job X used 65 machine-hours and it
At the beginning of the year, a company estimated a predetermined plantwide overhead rate of $8.50 per machinehour. Job X used 65 machine-hours and it was charged $200 and $288 for direct materials and direct labor, espectively. What is the total job cost for Job X? Multiple Choice $488.00 $552.50 $397.00 $1,040.50