Question

1 Approved Answer

Below are the critical activities of a PERT diagram. The optimistic time (a), most likely time (m), and pessimistic time (b) are shown at the

Below are the critical activities of a PERT diagram. The optimistic time (a), most likely time (m), and pessimistic time (b) are shown at the bottom of each activity. Calculate the most likely time (t,) for each activity.

image text in transcribed

  1. Calculate the optimistic, pessimistic, and expected time for completing the project [6]
  2. Determine the probability that this project can be completed in 38 days [4]
  3. What is the probability that this project will be completed by the thirty-second day? [4]
  4. For a 99% probability, determine the expected number of days for completion [3]
  5. For a 1% probability, determine the expected number of days for completion [3]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cyber Security And Supply Chain Management

Authors: Steven Carnovale, Sengun Yeniyurt

1st Edition

9811231567, 978-9811231568

More Books

Students also viewed these General Management questions