Question
CHOOSE THE CORRECT ANSWER 1) The cement contractor is scheduled to pour the cement on 15th of March. They cannot do it sooner or later.
CHOOSE THE CORRECT ANSWER
1) The cement contractor is scheduled to pour the cement on 15th of March. They cannot do it sooner or later. This is an example of
- Start to Finish
- Constraint
- Dependency
- Finish to Start
2) The image below indicates:
- Start to start dependency between L and J
- Finish to finish dependency between L and J
- Start to finish dependency between L and J
- Finish to start dependency between L and J
3) Developers are accountable for what?
- Adapting their plan to Spring Goal
- Holding each other professional
- All of the other answers
- The Sprint Plan
4) Dependency means some activity's start or finish is dependent on another activity
- True
- False
5) The following is a good milestone section for the project charter:
Project Start
Planning the project
Making prototype
Finalizing the design
Development
Project Fisnish
- True
- False
6) Projects, programs, subsidiary portfolios, and operations is called
- Projects
- Program
- Portfolio
- Process
7) Project manager role in traditional project management is exactly the same as the role of Scrum master in Scrum framework.
- True
- False
8) In lessons learned meeting we try to get to the root cause of the issues.
- True
- False
9) Who most likely creates the Business case?
- Customer
- Product manager
- Team members
- Project manager
10) During the closing phase a project plan can be used to assess project success.
- True
- False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started