cises (1 pt) 6 Saved Help Highlands Company uses the weighted average method in its process costing system. It processes wood pulp for various manufacturers of paper products. Data relating to tons of pulp processed during June are provided below: Percent Completed Labor and Tons of Pulp Materials Overhead 81,900 86 23 50,700 498 178 300,400 Work in process, June 1 Work in process, June 30 Started into production during June ces Required: 1. Compute the number of tons of pulp completed and transferred out during June. 2. Compute the equivalent units of production for materials and for labor and overhead for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the number of tons of pulp completed and transferred out during June. Tons completed and transferred out Required Required 2 > aw Exercises (1 pt) Saved Help Sa Highlands Company uses the weighted average method in its process costing system. It processes wood pulp for various manufacturers of paper products. Data relating to tons of pulp processed during June are provided below: Percent Completed Labor and Tons of Pulp Materials Overhead 81,900 86 23 50,700 498 173 300, 400 Work in process, June 1 Work in process, June 30 Started into production during June eBook Print eferences Required: 1. Compute the number of tons of pulp completed and transferred out during June. 2. Compute the equivalent units of production for materials and for labor and overhead for June. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the equivalent units of production for materials and for labor and overhead for June. BE Materials Labor and Overhead Equivalent units of production DT