Dr . Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly - line balancing. The assembly - line activities are: Task Performance

Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. The assembly-line activities are:
Task
Performance
Time(mins)
Predecessors
Task
Performance
Time(mins)
Predecessors
A
44
minus
G
55
F
B
66
minus
H
77
D, E
C
88
A
I
22
H
D
77
A, B
J
88
E
E
33
B
K
22
G, I, J
F
44
C
a) For the given daily (2424-hour) production rate of 120120units, the highest allowable cycle time=1212 minutes (enter your response as a whole number).
b) If the cycle time is given as 1010minutes, then the effective daily (2424-hour) production rate=144144 units (enter your response as a whole number).
c) For the given 1010-minute cycle time, the theoretical minimum number of workstations=66(round your response up to the next whole number).
d) The correct precedence relationship with one of the possible assignments of tasks to workstations for the given 1010-minute cycle time is shown in
Fig. 1
.
font size increased by 4 Upper AA font size increased by 4 Upper GG font size increased by 4 Upper HH font size increased by 4 Upper BB font size increased by 4 Upper CC font size increased by 4 Upper DD font size increased by 4 Upper JJ font size increased by 4 Upper II font size increased by 4 Fig. 1Fig. 1 font size increased by 4 Upper FF font size increased by 4 Upper EE font size increased by 4 Upper KK
x y graph
font size increased by 4 Upper AA font size increased by 4 Upper GG font size increased by 4 Upper HH font size increased by 4 Upper BB font size increased by 4 Upper EE font size increased by 4 Upper CC font size increased by 4 Upper JJ font size increased by 4 Upper II font size increased by 4 Fig. 2Fig. 2 font size increased by 4 Upper FF font size increased by 4 Upper DD font size increased by 4 Upper KK
x y graph
font size increased by 4 Upper AA font size increased by 4 Upper GG font size increased by 4 Upper HH font size increased by 4 Upper BB font size increased by 4 Upper CC font size increased by 4 Upper DD font size increased by 4 Upper JJ font size increased by 4 Upper II font size increased by 4 Fig. 3Fig. 3 font size increased by 4 Upper FF font size increased by 4 Upper EE font size increased by 4 Upper KK
x y graph
e) The operating efficiency of the assembly line =93.3393.33%(enter your response as a percentage rounded to two decimal places).
f) The idle time for the assembly line per cycle=44 minutes (enter your response as a whole number).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

ISBN: 470533013, 978-0470533017

More Books

Students also viewed these General Management questions