Five tasks are scheduled to be completed in sequence. Each task has a finish - * start relationship with the next task. Each has one
Five tasks are scheduled to be completed in sequence. Each task has a finish start relationship with the next task. Each has one day of total float. As of today, task one and two have been completed on schedule. How many days of float remain in the schedule of these tasks?