Given the fact that the number of skiing visitors to Whistler, B . C . , Canada, has been increasing at an exciting rate, thanks
Given the fact that the number of skiing visitors to Whistler, BC Canada, has been
increasing at an exciting rate, thanks to the Winter Olympics, the Whistler Ski
Association has been considering construction of another ski lodge and ski complex. The
results of an economic feasibility study just completed by members of the staff show that a
winter resort complex near the base of Whistler Mountain could be a very profitable
venture. The area is accessible by car, bus, train, and air. The board of directors has voted
to build the milliondollar complex recommended in the study. Unfortunately, due to
the short summer season, the complex will have to be built in stages. The first stage year
will contain a day lodge, chair lift, rope tow, generator house for electricity and
parking lot designed to accommodate cars and buses. The second and third stages
will include a hotel, an ice rink, a pool, shops, two additional chair lifts, and other
attractions. The board has decided that stage one should begin no later than April and be
completed by October in time for the next skiing season. You have been assigned the
task of project manager, and it is your job to coordinate the ordering of materials and
construction activities to ensure the projects completion by the required date.
After looking into the possible sources of materials, you are confronted with the
following time estimates. Materials for the chair lift and rope tow will take days and
days, respectively, to arrive once the order is submitted. Lumber for the day lodge,
generator hut, and foundations will take days to arrive. The electrical and plumbing
materials for the day lodge will take days to arrive. The generator will take days to
arrive. Before actual construction can begin on the various facilities, a road to the site must
be built; this will take days. As soon as the road is in clearing can begin concurrently on
the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the
clearing task at each site will take days, days, days, and days, respectively. The
clearing of the main ski slopes can begin after the area for the chair lift has been cleared;
this will take days.
The foundation for the day lodge will take days to complete. Construction of the
main framework will take an additional days. After the framework is completed,
electrical wiring and plumbing can be installed concurrently. These should take and
days, respectively. Finally, the finishing construction on the day lodge can
begin; this will take days.
Installation of the chair lift towers days can begin once the site is cleared, lumber
delivered, and foundation completed days Also, when the chair lift site has been
cleared, construction of a permanent road to the upper towers can be started; this will take
days. While the towers are being installed, the electric motor to drive the chair lift can
be installed; the motor can be installed in days. Once the towers are completed and the
motor installed, it will take days to install the cable and an additional days to install
the chairs.
Installation of the towers for the rope tow can begin once the site is cleared and the
foundation is built and poured; it takes days to build the foundation, pour the concrete,
and let it cure and days to install the towers for the rope tow. While the towers are being
erected, installation of the electric motor to drive the rope tow can begin; this activity will
take days. After the towers and motor are installed, the rope tow can be strung in day.
The parking lot can be cleared once the rope tow is finished; this task will take days.
The foundation for the generator house can begin at the same time as the foundation
for the lodge; this will take days. The main framework for the generator house can begin
once the foundation is completed; framing will take days. After the house is framed, the
diesel generator can be installed in days. Finishing construction on the generator house
can now begin and will take more days.
Assignment
Identify the critical path on your network.
Can the project be completed by October
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started