Given the fact that the number of skiing visitors to Whistler, B . C . , Canada, has been increasing at an exciting rate, thanks

Given the fact that the number of skiing visitors to Whistler, B.C., Canada, has been
increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski
Association has been considering construction of another ski lodge and ski complex. The
results of an economic feasibility study just completed by members of the staff show that a
winter resort complex near the base of Whistler Mountain could be a very profitable
venture. The area is accessible by car, bus, train, and air. The board of directors has voted
to build the 10-million-dollar complex recommended in the study. Unfortunately, due to
the short summer season, the complex will have to be built in stages. The first stage (year
1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and
parking lot designed to accommodate 400 cars and 30 buses. The second and third stages
will include a hotel, an ice rink, a pool, shops, two additional chair lifts, and other
attractions. The board has decided that stage one should begin no later than April 1 and be
completed by October 1, in time for the next skiing season. You have been assigned the
task of project manager, and it is your job to coordinate the ordering of materials and
construction activities to ensure the projects completion by the required date.
After looking into the possible sources of materials, you are confronted with the
following time estimates. Materials for the chair lift and rope tow will take 30 days and 12
days, respectively, to arrive once the order is submitted. Lumber for the day lodge,
generator hut, and foundations will take 9 days to arrive. The electrical and plumbing
materials for the day lodge will take 12 days to arrive. The generator will take 12 days to
arrive. Before actual construction can begin on the various facilities, a road to the site must
be built; this will take 6 days. As soon as the road is in, clearing can begin concurrently on
the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the
clearing task at each site will take 6 days, 3 days, 36 days, and 6 days, respectively. The
clearing of the main ski slopes can begin after the area for the chair lift has been cleared;
this will take 84 days.
The foundation for the day lodge will take 12 days to complete. Construction of the
main framework will take an additional 18 days. After the framework is completed,
electrical wiring and plumbing can be installed concurrently. These should take 24 and 30
days, respectively. Finally, the finishing construction on the day lodge can
begin; this will take 36 days.
Installation of the chair lift towers (67 days) can begin once the site is cleared, lumber
delivered, and foundation completed (6 days). Also, when the chair lift site has been
cleared, construction of a permanent road to the upper towers can be started; this will take
24 days. While the towers are being installed, the electric motor to drive the chair lift can
be installed; the motor can be installed in 24 days. Once the towers are completed and the
motor installed, it will take 3 days to install the cable and an additional 12 days to install
the chairs.
Installation of the towers for the rope tow can begin once the site is cleared and the
foundation is built and poured; it takes 4 days to build the foundation, pour the concrete,
and let it cure and 20 days to install the towers for the rope tow. While the towers are being
erected, installation of the electric motor to drive the rope tow can begin; this activity will
take 24 days. After the towers and motor are installed, the rope tow can be strung in 1 day.
The parking lot can be cleared once the rope tow is finished; this task will take 18 days.
The foundation for the generator house can begin at the same time as the foundation
for the lodge; this will take 6 days. The main framework for the generator house can begin
once the foundation is completed; framing will take 12 days. After the house is framed, the
diesel generator can be installed in 18 days. Finishing construction on the generator house
can now begin and will take 12 more days.
Assignment
1. Identify the critical path on your network.
2. Can the project be completed by October 1?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions

Question

LO4 Describe what is meant by the term supply-side economics.

Answered: 1 week ago