Given the table below: Activity Dependency Duration Normal Direct Cost ($000) Max Crash Time Total Crash Cost ($000) A 10 20 N/A B A 30

Given the table below:

Activity

Dependency

Duration

Normal

Direct Cost

($000)

Max Crash Time

Total Crash Cost($000)

A

10

20

N/A

B

A

30

60

1

5

C

B

30

50

3

15

D

B

22

80

3

4.5

E

C

20

30

5

3

F

D

32

50

3

3

G

E,F

20

20

2

4

If the indirect cost savings is $1,400 per day:

Provide the steps and process to crash this project

What is the maximum time that this project can be crashed and what is the new duration? What is the optimal time that this project can be crashed and what would be the new duration? What are the extra costs for each?

Provide the final network diagram (using the maximum crash time)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

12th edition

134741064, 9780273766834, 027376683X, 9780273766940, 273766945, 9780273766841, 273766848, 978-0134741062

More Books

Students also viewed these General Management questions