Question
Given the table below: Activity Dependency Duration Normal Direct Cost ($000) Max Crash Time Total Crash Cost ($000) A 10 20 N/A B A 30
Given the table below:
Activity | Dependency | Duration | Normal Direct Cost ($000) | Max Crash Time | Total Crash Cost($000) |
A |
| 10 | 20 | N/A |
|
B | A | 30 | 60 | 1 | 5 |
C | B | 30 | 50 | 3 | 15 |
D | B | 22 | 80 | 3 | 4.5 |
E | C | 20 | 30 | 5 | 3 |
F | D | 32 | 50 | 3 | 3 |
G | E,F | 20 | 20 | 2 | 4 |
If the indirect cost savings is $1,400 per day:
Provide the steps and process to crash this project
What is the maximum time that this project can be crashed and what is the new duration? What is the optimal time that this project can be crashed and what would be the new duration? What are the extra costs for each?
Provide the final network diagram (using the maximum crash time)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started