QUESTION 11 Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,000 Training of machine operators 28,000 Processing returned products 19,000 Scrap processing
QUESTION 11
Schedule of Activity Costs
Quality Control Activities | Activity Cost |
Process audits | $50,000 |
Training of machine operators | 28,000 |
Processing returned products | 19,000 |
Scrap processing (disposal) | 25,000 |
Rework | 8,000 |
Preventative maintenance | 30,000 |
Product design | 46,000 |
Warranty work | 12,000 |
Finished goods inspection | 23,000 |
From the above schedule of activity costs, determine the total activity cost.
a. | $241,000 | |
b. | $179,000 | |
c. | $62,000 | |
d. | $94,000 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started