Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTION 4 Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system.
QUESTION 4 Carlos Gonzales is production manager at an assembly plant that manufactures cordless telephones. The company is planning to install a pull system. The process is being planned to have a usage rate of 35 pieces per hour. Each container is designed to hold 15 pieces. It takes an average of 30 minutes to complete a cycle. How many containers will be needed? (Calculate to 2 decimal places)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started