SOFTWARE ENGINEERING USE CASE PROBLEM: 1. Scope: Business 2. Level: User goal 3. Primary actor: Project Manager Order right amount of right supply Get supply
SOFTWARE ENGINEERING USE CASE PROBLEM:
1.Scope: Business
2.Level: User goal
3.Primary actor: Project Manager Order right amount of right supply
Get supply to site at right time
4.Stakeholders, Interests, and Secondary Actors
Site Supervisor Actor Ensure supplies needed in near future available
Purchasing Actor Ensure purchase orders and payments issued
Accts Payable/Receiv Actor Issue proper payment after delivery
Supplier Actor Provide supply to site as contracted; get paid
Shipper Actor Deliver supply to site as contracted; get paid
Site Security Actor Ensure supply is secure and in condition for use
(if required)
Traffic authorities Actor Ensure delivery does not conflict with events
Provide traffic rerouting or control if needed
Customer Offstage Ensure progress on construction
Corporate Offstage Ensure progress on construction
Tax officials Offstage Ensure all taxes and fees are paid
Authentication System
Inventory System
Supplier & Shipper DB System
Project parts DB System
Project records DB System
Corporate accounts System
5.Preconditions
Supply is needed for project immediately or in near future
Item not yet in inventory or amount insufficient
Part(s), supplier and shipper identified
Space to store supply exists, with needed security and other storage conditions
6.Success guarantee
The right part(s) have been ordered, supplied, shipped, delivered and stored as needed
Delivery was on time
The part(s) are in good condition and ready for use when needed
Supplier and shipper have been given receipts and paid
All records have been updated to reflect transaction
7.Main success scenario
Project Manager consults Project Schedule in Project Records DB
Project Manager determines supply/supplies needed
System authenticates Project Manager
Project Manager consults Project Parts DB and identifies Part(s)
Project Manager selects amount for each Part
Project Manager notifies Purchasing with Part Identifier(s), amount(s), and date needed
For each Part {
7.Purchasing identifies Supplier
Purchasing generates Purchase Order and sends to Supplier
Purchasing records Purchase Order in Corporate Accounts DB
Supplier receives Purchase Order
Supplier assembles and packages Part(s) and notifies Purchasing
Supplier identifies Shipper and arranges shipment
Shipper contacts Traffic Authorities to clear plan of delivery, if needed
Shipper loads Part(s) and notifies Project Manager of arrival date and expected time
Shipper delivers and unloads Part(s)
System authenticates Site Supervisor
Site Supervisor certifies on-time receipt of proper Part(s) in good condition
Site Security transfers Part(s) to appropriate storage
Site Supervisor notifies Project Manager
Project Manager records receipt in Project Records DB
Project Manager updates Inventory and notifies Purchasing
Purchasing records delivery in Corporate Accounts DB and notifies Accounts P/R
Accounts P/R arranges and delivers payment for Supplier and Shipper
Accounts P/R records payments in Corporate Accounts DB
Shipper and Supplier acknowledge payment
Accounts P/R records acknowledgements
}
Alternate flows
Project Manager cannot be authenticatedRetry until retryCount exceeded
If successful, re-enter at Step 4
Retry at corporate HQ
Re-enter at Step 4
Part(s) cannot be identified
Need to write a handler for thisfind part, clear with Purchasing
Re-enter at step 5
PM cannot contact Purchasing
No Supplier exists or Supplier cannot be contacted
Identify alternative Supplier
Shorthand [t1]not necessarily a database.
Next two items ditto.
[t2]Could write a use case where choice of shipper and supplier are subfunction use cases
[t3]Standard loop construction
Ignores the likelihood that multiple parts will come from the same Supplier. Could be handled with a nested loop on Supplier and Part.
[t4]Authentication of Purchasing and Accounts P/R is out of scope. Supplier and Shipper are not in-house. This Business Use Case is written from a
Limited [t5]simple if-then conditional flow is OK, especially if its deferral to Alternative Flows makes things more complicated than putting it in
[t6]Project Manager may need re-authentication
***********QUESTION**************
Develop the Alternative Flows for a Fully-Dressed Use Case, for the Order On-Line Supplies Use Case.you should look at Larman's ProcessSale Use Case as well as the partial Fully-Dressed Use Case for RegisterStudent we discussed earlier in the term.
Remember, however, that this is a Business-level use case, so your alternative flows should involve system elements only as actors in the case, and these should (almost always) be those identified as actors in the partially developed use case, posted under Project Documents.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started