Which of the following techniques is not used to manage Risks? Select one: a. Ensure risk mitigation plans are integrated with project plansb. Document the
Which of the following techniques is not used to manage Risks?
Select one:
a. Ensure risk mitigation plans are integrated with project plansb. Document the rationale used when closing a riskc. Ensure the executive sponsor weighs in on every risk in the registerd. Enlist a liaison between IT and the business community to assist in addressing cultural risks.