Using the master schedule, and the product structures, determine the time-phased requirements for component C6 and raw

Question:

Using the master schedule, and the product structures, determine the time-phased requirements for component C6 and raw material M6. The raw material used in component C6 is M6. Lead times are as follows: for P1, assembly lead time is 1 week; for P2, assembly lead time is 1 week; for S2, assembly lead time is 1 week; for S3, assembly lead time is 1 week; for C6, manufacturing lead time is 2 weeks; and for M6, ordering lead time is 2 weeks. Assume that the current inventory status for all of the above items is zero units on hand, and zero units on order. The format of the solution should be similar to that presented in.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: