For the following process, management has hired a new worker for station D. The new hire works at a cycle time (CT) of 16 mins
For the following process, management has hired a new worker for station D. The new hire works at a cycle time (CT) of 16 mins per unit. What is the new capacity of station D in units per hour after adding the new hire? Enter your answer rounded to 2 decimal places. (New hire is not shown in the process diagram below. The new hire is the only addition and no workers are removed.) new hire A.png